Dholera developers ranked by months from project start to GujRERA registration
Updated 17 November 2026. Compiled by the dholera.blog desk from the sources listed at the end of this page.
On the GujRERA register read on 17 November 2026, 16 of the 33 registered Dholera projects were registered within three months of their declared start date. The shortest gap is two months, shared by 7 Oak Platinum 4, Aaiji Residency and Dholera Marigold 548 among others; the longest is 12 months, Fidato Luxuria 2. The median gap is 4 months.
- 33registered projects compared
- 2 monthsshortest gap between start and registration
- 12 monthslongest gap
- 4 monthsmedian gap
Registered projects by months from start to registration
| Rank | Promoter (as on the record) | Project | GujRERA number | Village | Project start date | Registration date | Gap (months) |
|---|---|---|---|---|---|---|---|
| 1 | 7 OAK DEVELOPERS | 7 OAK PLATINUM 4 | PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA07741/051220 | Kadipur ( Dholera ) | 3 October 2020 | 5 December 2020 | 2 |
| 1 | AAIJI INFRA AND DEVELOPERS | AAIJI RESIDENCY | PR/GJ/AHMEDABAD/DHANDHUKA/AUDA/PAA09145/111021 | Not stated in the record | 24 August 2021 | 11 October 2021 | 2 |
| 1 | Bhaveshkumar C. Hakani Proprietor of C T CORPORATION | DHOLERA MARIGOLD 548 | PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA07648/091120 | Kadipur | 19 September 2020 | 9 November 2020 | 2 |
| 1 | CHHABILDAS DEVELOPERS PRIVATE LIMITED | DHOLERA SKY | PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA07924/160121 | Not stated in the record | 5 November 2020 | 16 January 2021 | 2 |
| 1 | CUBE INFRASTRUCTURE | NEST 63 | PR/GJ/AHMEDABAD/AHMEDABAD CITY/Others/PAA10662/150922 | Not stated in the record | 15 July 2022 | 15 September 2022 | 2 |
| 1 | GAP ASSOCIATES PRIVATE LIMITED | GAP Industrial Park 1 | PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA10173/EX1/030826/311226 | Not stated in the record | 14 March 2022 | 11 May 2022 | 2 |
| 1 | GAP STUDIOS LLP | Aakar | PR/GJ/AHMEDABAD/DHOLERA/DSIRDA/RAA15713/190825/311228 | Bhimtalav | 17 June 2025 | 19 August 2025 | 2 |
| 1 | GREENERA INFRAWELL PRIVATE LIMITED | GREENERA GARDENVILLA 2 | PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA11450/EX1/010925/300526 | Not stated in the record | 17 January 2023 | 14 March 2023 | 2 |
| 1 | GREENERA INFRAWELL PRIVATE LIMITED | GREENERA PRIME 2 | PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA07841/311220 | Kadipur | 6 November 2020 | 31 December 2020 | 2 |
| 1 | PARV INFRACON LLP | SHANTIBAN DREAMS | PR/GJ/AHMEDABAD/AHMEDABAD CITY/Dholera Special Investment Region Development Authority/MAA11736/A1M/281026/311228 | DHOLERA | 2 March 2023 | 8 May 2023 | 2 |
| 1 | Shyam Infra | Dholera Iconic | PR/GJ/AHMEDABAD/DHOLERA/DSIRDA/CAA16655/010426/310330 | Mundi | 2 February 2026 | 1 April 2026 | 2 |
| 12 | 7 OAK DEVELOPERS | 7 OAK SMART CITY | PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA07929/180121 | Not stated in the record | 29 October 2020 | 18 January 2021 | 3 |
| 12 | 7 OAK DEVELOPERS | PLATINUM 7 | PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA08002/030221 | Not stated in the record | 5 November 2020 | 3 February 2021 | 3 |
| 12 | CUBE INFRA | NEST 29 | PR/GJ/AHMEDABAD/DHANDHUKA/AUDA/PAA07781/161220 | Dholera | 28 September 2020 | 16 December 2020 | 3 |
| 12 | GREENERA INFRAWELL PRIVATE LIMITED | GREENERA GARDENVILLA | PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA07425/EX1/EX2/220825/301225 | Bhimtalav | 1 June 2020 | 5 September 2020 | 3 |
| 12 | SEKSARIA BUILDCON LLP | SHANTIBAN SKYLAR | PR/GJ/AHMEDABAD/DHOLERA/DSIRDA/MAA16212/151225/311229 | DHOLERA | 13 September 2025 | 15 December 2025 | 3 |
| 17 | 7 OAK DEVELOPERS PRIVATE LIMITED | PLATINUM 9 | PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA10275/060622 | Not stated in the record | 4 February 2022 | 6 June 2022 | 4 |
| 17 | PACIFICUS SUPERINFRA LLP | PALM GREENS PLATINUM 2 | PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA09395/EX1/240326/311226 | Not stated in the record | 12 August 2021 | 1 December 2021 | 4 |
| 17 | Ruturajsinh Jagdishsinh Chudasama(Proprietor of Infinity Infracon ) | PARK VIEW | PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA10465/180722 | Not stated in the record | 1 April 2022 | 18 July 2022 | 4 |
| 20 | 7 OAK DEVELOPERS | Platinum 8 | PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA08209/170321 | Not stated in the record | 29 October 2020 | 17 March 2021 | 5 |
| 20 | AAIJI INFRASPACE(OPC)PRIVATE LIMITED | AAIJI RESIDENCY 477 | PR/GJ/AHMEDABAD/DHOLERA/DSIRDA/PAA15497/110725/311229 | KADIPUR | 1 February 2025 | 11 July 2025 | 5 |
| 20 | DHOLERA MEGA CITY 771 | Dholera Megacity 771 | PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA10217/200522 | Not stated in the record | 1 January 2022 | 20 May 2022 | 5 |
| 20 | SMART DHOLERA HOUSING PRIVATE LIMITED | PICCADILLY SQUARE II | PR/GJ/AHMEDABAD/DHOLERA/DSIRDA/PN36AA09936/210522 | KADIPUR | 23 December 2021 | 21 May 2022 | 5 |
| 24 | FIDATO BUILDCON | FIDATO LUXURIA 3 | PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA08562/040621 | Not stated in the record | 29 October 2020 | 4 June 2021 | 7 |
| 25 | SMARTHOMES INFRASTRUCTRE PRIVATE LIMITED | ABCD ENCLAVE IV | PR/GJ/AHMEDABAD/DHANDHUKA/DSIRDA/PN70AA09970/080622 | BHADIYAD | 6 October 2021 | 8 June 2022 | 8 |
| 26 | FIDATO BUILDCON | Fidato Luxuria | PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA07658/101120 | Dholera | 30 January 2020 | 10 November 2020 | 9 |
| 26 | Ruturajsinh Jagdishsinh Chudasama(Proprietor of Infinity Infracon ) | Dholera Megacity Iris | PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA10133/020522 | Not stated in the record | 12 August 2021 | 2 May 2022 | 9 |
| 26 | SATYAJA INFRATECH | BLISS 107 | PR/GJ/AHMEDABAD/DHOLERA/DSIRDA/PAA12751/040124/310328 | KADIPUR | 1 April 2023 | 4 January 2024 | 9 |
| 29 | SATYAJA INFRACON | BLISS GRANDEUR- 1 | PR/GJ/AHMEDABAD/DHOLERA/DSIRDA/PAA12734/030124/310328 | KADIPUR | 1 March 2023 | 3 January 2024 | 10 |
| 29 | SATYAJA INFRACON | BLISS GRANDEUR- 2 | PR/GJ/AHMEDABAD/DHOLERA/DSIRDA/PAA12719/211223/310328 | KADIPUR | 1 March 2023 | 21 December 2023 | 10 |
| 31 | GREENERA INFRAWELL PRIVATE LIMITED | GREENERA PRIME 1 | PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA07785/161220 | Kadipur | 1 January 2020 | 16 December 2020 | 11 |
| 31 | SATYAJA INFRATECH | PRELUDE INDUSTRIAL PARK | PR/GJ/AHMEDABAD/DHOLERA/DSIRDA/PAA12807/240124/310328 | AMBLI | 1 March 2023 | 24 January 2024 | 11 |
| 33 | FIDATO BUILDCON | FIDATO LUXURIA 2 | PR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA09239/271021 | Not stated in the record | 29 October 2020 | 27 October 2021 | 12 |
All 33 registered projects have both dates (0 dropped for a missing date). Months are the days between the two dates divided by 30.44, rounded. Shortest gap first; ties share a rank. Read on 2026-11-17.
Download this table (CSV). Last checked 17 November 2026. Free to quote with a link to this page.
Bars show the first 15 rows, shortest gap first.
1. 7 OAK DEVELOPERS, 7 OAK PLATINUM 4
- GujRERA numberPR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA07741/051220
- VillageKadipur ( Dholera )
- Project start date3 October 2020
- Registration date5 December 2020
- Gap2 months
The record gives a project start date of 3 October 2020 and a registration date of 5 December 2020, a gap of 2 months. The registration date is the approval date on the GujRERA record.
The start date is the one the promoter entered for the project. A gap does not show when sales began or when work began on site, and the register does not explain it.
2. AAIJI INFRA AND DEVELOPERS, AAIJI RESIDENCY
- GujRERA numberPR/GJ/AHMEDABAD/DHANDHUKA/AUDA/PAA09145/111021
- VillageNot stated in the record
- Project start date24 August 2021
- Registration date11 October 2021
- Gap2 months
The record gives a project start date of 24 August 2021 and a registration date of 11 October 2021, a gap of 2 months. The registration date is the approval date on the GujRERA record.
The start date is the one the promoter entered for the project. A gap does not show when sales began or when work began on site, and the register does not explain it.
3. Bhaveshkumar C. Hakani Proprietor of C T CORPORATION, DHOLERA MARIGOLD 548
- GujRERA numberPR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA07648/091120
- VillageKadipur
- Project start date19 September 2020
- Registration date9 November 2020
- Gap2 months
The record gives a project start date of 19 September 2020 and a registration date of 9 November 2020, a gap of 2 months. The registration date is the approval date on the GujRERA record.
The start date is the one the promoter entered for the project. A gap does not show when sales began or when work began on site, and the register does not explain it.
4. CHHABILDAS DEVELOPERS PRIVATE LIMITED, DHOLERA SKY
- GujRERA numberPR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA07924/160121
- VillageNot stated in the record
- Project start date5 November 2020
- Registration date16 January 2021
- Gap2 months
The record gives a project start date of 5 November 2020 and a registration date of 16 January 2021, a gap of 2 months. The registration date is the approval date on the GujRERA record.
The start date is the one the promoter entered for the project. A gap does not show when sales began or when work began on site, and the register does not explain it.
5. CUBE INFRASTRUCTURE, NEST 63
- GujRERA numberPR/GJ/AHMEDABAD/AHMEDABAD CITY/Others/PAA10662/150922
- VillageNot stated in the record
- Project start date15 July 2022
- Registration date15 September 2022
- Gap2 months
The record gives a project start date of 15 July 2022 and a registration date of 15 September 2022, a gap of 2 months. The registration date is the approval date on the GujRERA record.
The start date is the one the promoter entered for the project. A gap does not show when sales began or when work began on site, and the register does not explain it.
6. GAP ASSOCIATES PRIVATE LIMITED, GAP Industrial Park 1
- GujRERA numberPR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA10173/EX1/030826/311226
- VillageNot stated in the record
- Project start date14 March 2022
- Registration date11 May 2022
- Gap2 months
The record gives a project start date of 14 March 2022 and a registration date of 11 May 2022, a gap of 2 months. The registration date is the approval date on the GujRERA record.
The start date is the one the promoter entered for the project. A gap does not show when sales began or when work began on site, and the register does not explain it.
7. GAP STUDIOS LLP, Aakar
- GujRERA numberPR/GJ/AHMEDABAD/DHOLERA/DSIRDA/RAA15713/190825/311228
- VillageBhimtalav
- Project start date17 June 2025
- Registration date19 August 2025
- Gap2 months
The record gives a project start date of 17 June 2025 and a registration date of 19 August 2025, a gap of 2 months. The registration date is the approval date on the GujRERA record.
The start date is the one the promoter entered for the project. A gap does not show when sales began or when work began on site, and the register does not explain it.
8. GREENERA INFRAWELL PRIVATE LIMITED, GREENERA GARDENVILLA 2
- GujRERA numberPR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA11450/EX1/010925/300526
- VillageNot stated in the record
- Project start date17 January 2023
- Registration date14 March 2023
- Gap2 months
The record gives a project start date of 17 January 2023 and a registration date of 14 March 2023, a gap of 2 months. The registration date is the approval date on the GujRERA record.
The start date is the one the promoter entered for the project. A gap does not show when sales began or when work began on site, and the register does not explain it.
9. GREENERA INFRAWELL PRIVATE LIMITED, GREENERA PRIME 2
- GujRERA numberPR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA07841/311220
- VillageKadipur
- Project start date6 November 2020
- Registration date31 December 2020
- Gap2 months
The record gives a project start date of 6 November 2020 and a registration date of 31 December 2020, a gap of 2 months. The registration date is the approval date on the GujRERA record.
The start date is the one the promoter entered for the project. A gap does not show when sales began or when work began on site, and the register does not explain it.
10. PARV INFRACON LLP, SHANTIBAN DREAMS
- GujRERA numberPR/GJ/AHMEDABAD/AHMEDABAD CITY/Dholera Special Investment Region Development Authority/MAA11736/A1M/281026/311228
- VillageDHOLERA
- Project start date2 March 2023
- Registration date8 May 2023
- Gap2 months
The record gives a project start date of 2 March 2023 and a registration date of 8 May 2023, a gap of 2 months. The registration date is the approval date on the GujRERA record.
The start date is the one the promoter entered for the project. A gap does not show when sales began or when work began on site, and the register does not explain it.
11. Shyam Infra, Dholera Iconic
- GujRERA numberPR/GJ/AHMEDABAD/DHOLERA/DSIRDA/CAA16655/010426/310330
- VillageMundi
- Project start date2 February 2026
- Registration date1 April 2026
- Gap2 months
The record gives a project start date of 2 February 2026 and a registration date of 1 April 2026, a gap of 2 months. The registration date is the approval date on the GujRERA record.
The start date is the one the promoter entered for the project. A gap does not show when sales began or when work began on site, and the register does not explain it.
12. 7 OAK DEVELOPERS, 7 OAK SMART CITY
- GujRERA numberPR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA07929/180121
- VillageNot stated in the record
- Project start date29 October 2020
- Registration date18 January 2021
- Gap3 months
The record gives a project start date of 29 October 2020 and a registration date of 18 January 2021, a gap of 3 months. The registration date is the approval date on the GujRERA record.
The start date is the one the promoter entered for the project. A gap does not show when sales began or when work began on site, and the register does not explain it.
13. 7 OAK DEVELOPERS, PLATINUM 7
- GujRERA numberPR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA08002/030221
- VillageNot stated in the record
- Project start date5 November 2020
- Registration date3 February 2021
- Gap3 months
The record gives a project start date of 5 November 2020 and a registration date of 3 February 2021, a gap of 3 months. The registration date is the approval date on the GujRERA record.
The start date is the one the promoter entered for the project. A gap does not show when sales began or when work began on site, and the register does not explain it.
14. CUBE INFRA, NEST 29
- GujRERA numberPR/GJ/AHMEDABAD/DHANDHUKA/AUDA/PAA07781/161220
- VillageDholera
- Project start date28 September 2020
- Registration date16 December 2020
- Gap3 months
The record gives a project start date of 28 September 2020 and a registration date of 16 December 2020, a gap of 3 months. The registration date is the approval date on the GujRERA record.
The start date is the one the promoter entered for the project. A gap does not show when sales began or when work began on site, and the register does not explain it.
15. GREENERA INFRAWELL PRIVATE LIMITED, GREENERA GARDENVILLA
- GujRERA numberPR/GJ/AHMEDABAD/DHANDHUKA/Others/PAA07425/EX1/EX2/220825/301225
- VillageBhimtalav
- Project start date1 June 2020
- Registration date5 September 2020
- Gap3 months
The record gives a project start date of 1 June 2020 and a registration date of 5 September 2020, a gap of 3 months. The registration date is the approval date on the GujRERA record.
The start date is the one the promoter entered for the project. A gap does not show when sales began or when work began on site, and the register does not explain it.
Why I looked at this gap
Every project on the register carries two dates a buyer can read: the start date the promoter declared and the date the Authority approved the registration. Most pages about Dholera developers use neither. The gap between them is a fact anyone can check, and it is a better question to ask a seller than how many people have already booked. The gap is the builder's or developer's own declared start date set against the Authority's approval date.
This page records the gap and nothing more. The register does not say why a gap is two months or twelve, and I do not guess.
How to read the gap
The gap is counted from the project start date to the registration date. Across the 33 projects it runs from 2 to 12 months with a median of 4 months. 16 projects have a gap of three months or less and 8 have a gap of nine months or more.
The start date is the one the promoter entered. It can mean the date a layout was planned, a land parcel was assembled or work was started, and the record does not say which. The registration date is the date the project was approved on the register. A gap is therefore a pointer to a question, not an answer.
How to check the two dates yourself in five minutes
- Open gujrera.gujarat.gov.in and search the project name as printed in the table.
- Open the project's detail page and note the project start date.
- On the same record find the registration or approval date.
- Check that the registration number matches the one in the table.
- If you are being sold a plot, ask the seller which registration number covers it and compare its approval date with the date on your booking papers.
What the register can and cannot show
The register shows that a project is registered and when. A buyer who books before the registration date has no registration to point to on the day of booking, and the same record is where to check the date. The register does not show who sold what to whom, so the gap by itself says nothing about any sale.
The 33 registered projects are only part of the plotted and built supply near Dholera. A project that is not registered has no start date or registration date on this register and is not in the table.
What this list cannot tell you
This list cannot tell you when sales began, when work started on the ground or why a gap is long or short. The start date is entered by the promoter, and the register shows only the registered projects. A short gap is not a sign of quality and a long one is not a sign of a problem.
Questions people ask
How long after a Dholera project starts is it registered with GujRERA?
On the register read on 17 November 2026, the gap between the declared start date and the registration date runs from 2 to 12 months across 33 projects, with a median of 4 months. 16 projects were registered within three months of their declared start date. The start date is entered by the promoter.
Which Dholera project was registered fastest after its start date?
Several are tied at two months, including 7 Oak Platinum 4, Aaiji Residency, Aakar, Dholera Iconic, Dholera Marigold 548, Dholera Sky, GAP Industrial Park 1, Nest 63 and Shantiban Dreams. The table above lists every tie in alphabetical order by promoter name.
What does the project start date on a RERA record mean?
It is the start date the promoter declares for the project when applying. It may reflect planning, land assembly or the start of work, and the record does not say which. For that reason this page shows the date and the gap and does not interpret either.
Should I buy a plot before or after the project is registered?
Check the registration first. GujRERA shows the registration number and the approval date, and a promoter should be able to name the number covering your plot. If the number is not on the register or the approval date is after your booking date, ask the seller to explain in writing before you pay.
Is the gap between start and registration a reason to avoid a project?
No. The register does not say why a gap exists, and the table covers only registered projects. Use a long gap as a prompt to read the record and ask the developer about it, and check the title and the registered area for the exact plot as you would for any other project.
Read next
- The GujRERA check
- Dholera timeline of slipped dates
- What actually happens when you book a plot
- Is it safe to buy land in Dholera
- Dholera myths ledger
Sources
- GujRERA public register, Dholera project records (start and registration dates) (read 17 November 2026)
- GujRERA public project API, example record 10840 (7 Oak Platinum 4) (read 17 November 2026)
- GujRERA public project API, example record 27645 (Aakar) (read 17 November 2026)